The most substantial challenges have emerged within the Gateway process. The initial lack of precise requirements, coupled with resource constraints at the Building Safety Regulator (BSR), has resulted in significant delays. These delays directly impact project timelines, hindering the government's objectives of increasing housing supply and stimulating economic activity through infrastructure investment.
The Act's introduction initially sparked confusion regarding roles and responsibilities, particularly concerning the Principal Designer. This led to varied interpretations and a period of uncertainty. Yet, Tier One contractors have effectively adapted, updating their responsibility matrices and appointments to comply with the new regulations. Tier Two contractors and product suppliers, in contrast, have been slower to grasp their obligations, often continuing with "business as usual" without fully understanding their legal responsibilities.
The introduction of the Gateway process for high-risk buildings, a key component of the Act, has exposed significant resource limitations within the BSR. The regulator was evidently unprepared for the volume of applications it received. Whilst Gateway 1 (planning stage) has generally functioned well, Gateway 2 (pre-construction stage) has become a major bottleneck. The long-term impact of Gateway 3 (post-construction sign-off) remains to be seen.
The Building Safety Regulator (BSR) initially aimed to approve new construction projects within 12 weeks; however, assessment times have now extended to between 25 and 40 weeks, resulting in delays of 12 to 18 months in construction schedules. Student housing developer Unite has reported delays of up to six months due to BSR approvals, which stem from a shortage of assessors, a problem anticipated by the industry during the Act's development. This situation raises questions about the government's preparedness to meet its obligations. Compounding the regulator's challenges is the resignation of Peter Baker, the BSR's founding leader, along with the closure of some private inspectors supporting the BSR, further exacerbating the backlog By June 2023, only 2% of the 668 submitted applications had been processed within the required timeframe, with a 40% rejection rate. The BSR's resource limitations also prevented it from providing pre-application advice, leading to misunderstandings regarding submission requirements, high rejection rates due to inaccurate information, and increased rework and resubmission.
The Building Safety Act represents a positive step for the construction sector. As with any major legislation, building awareness and changing behaviours takes time. In the three years since its implementation, the sector's response has been gradual, and understanding and adoption remain below desired levels.
The Building Safety Regulator has faced significant operational challenges that have impacted the sector, prompting the government to acknowledge these shortcomings and implement strategic changes by combining the BSR and Product Safety regulators. This dedication to improving processes aims to fulfil manifesto commitments, though it remains to be seen whether these changes will lead to better outcomes. Nonetheless, the sector has undoubtedly witnessed progress over the past three years.